Insufficient mixing station output power

(1) within the cylinder occurs, external leakage, usually due to the eccentric rod installation, lubricating oil supply shortage, seals and sealing ring worn or damaged cylinder and piston rod with impurities resulting from such injuries. So, when the cylinder occurs inside and outside leakage, re-adjust the center of the piston rod, piston and cylinder to ensure concentricity; should always check the lubricator is working and reliable, to ensure the implementation of components oiled; when the seal ring and seal ring ring worn or damaged, shall be replaced; if impurities exist in the cylinder, should be promptly removed; piston rod has scars should be replaced.
(2) Precast concrete plant output force and movement is not smooth, generally pistons or piston rod is stuck due to poor lubrication, air supply is insufficient, or a condensate tank and impurities and other causes. In this regard, should be adjusted to the center of the piston rod; checking whether the work lubricator reliable; supply line is clogged. When the cylinder memory condensed water and impurities, should be promptly removed.
(3) of the buffer cylinder is poor, ready mix concrete plant because of a buffer seal wear or damage caused by the adjustment screw. At this point, you should replace the seals and adjusting screw.
(4) damage to the piston rod and the cylinder head, generally due to the eccentric rod installation work or buffer mechanism caused. In this regard, should be adjusted to the center position of the piston rod; changing the buffer seals or adjustment screws.

没有评论:

发表评论